Avenue D Improvements Phase II
Project Overview
The Avenue D project will replace old, inadequate public utility infrastructure with repair and resurfacing of the road from Second Street to Tenth Street.
| Timeline | Summer 2025 |
| Project Status | Pre-construction |
| Funding | Transportation Improvement Board (TIB) grant funding is being utilized for this project. |
What to expect
The Avenue D project is set to grind and overlay the project area following installation of new water, sewer, and stormwater utilities, as well as full depth repair of failing road sections. All existing utility services will be reconnected to the new installed infrastructure. The project will take place entirely within the City right-of-way of Avenue D from Second Street to Tenth Street and includes sewer, water, storm, curb ramps, asphalt grinding and paving, pavement markings, traffic control, temporary erosion and sediment controls, and other associated work. Expect lane closures and traffic revisions during construction. Some customers may experience brief interruptions to utility services.
This project includes:
- Upgrade/replacement of nine ADA ramps on both sides of Avenue D between McDonalds and Second Street. City staff determined these ramps to be out of compliance.
- Replacement of roughly 1,800 feet of 6” Cast Iron (CI) water main, including services, meter boxes, and fire hydrants along Avenue D from Second Street to Fifth Street.
- Replacement of approximately 300-foot-long section of 6” sanitary sewer in Avenue D from north of Fourth Street to Fifth Street.
- Grind and overlay of Avenue D from Second Street to extent of recent overlay limit just north of the McDonalds driveway.
- Installation of catch basins and approximately 1,700 feet of new storm drain piping in Avenue D between Fourth Street and Seventh Street.
| May 2025 | Project advertised for competitive bidding |
| July 2025 | Contractor selected |
| August 2025 | Construction begins |
| December 2025 | Construction scheduled for completion |
| Avenue D (Second Street - Tenth Street) Improvement | $4.6 million |
1. Will my driveway access be impacted?
Driveway access may be restricted for a short time, but the Contractor will make efforts to allow free ingress and egress with driveways.
2. Will there be any road or intersection closures?
Currently no full road or intersection closures are anticipated, however this may change during construction with adequate notice provided. There will be traffic control for any lane closures or work within vehicle travel lanes and Variable Message Signs (VMS) will be set out to deliver traffic control notices.
3. Will there be any work on my property?
The only portion of work that will require coordination with property owners will be reconnecting the water and sewer services to each property. Three (3) days' notice will be provided prior to any work on active water and sewer services.
Brennan Collins
City of Snohomish Project Engineer
425-903-1812
Email Brennan