Project Overview

Construction of intersection enhancements from two-way stop controlled to signalized intersection for increasing level-of-service (LOS) and turning movement safety.

TimelineSummer 2025
Project StatusPre-construction
FundingThis project utilizes construction federal funding awarded through a grant from Puget Sound Regional Council (PSRC) and administered through Washington State Department of Transportation (WSDOT).


What to expect

The project includes traffic signal installation, sidewalk, curb ramps, drainage, pavement markings, and other associated work. Expect lane closures and traffic revisions during construction. 
  1. FAQs
  2. Contact

1. Will the intersection or any roads be closed for the project?


No roads nor the Bickford Ave and Weaver Road intersection will be completely closed.

2. Will there be traffic delays?


Yes, there will be traffic delays due to traffic control in place to route vehicles around the work site.

3. Will the configuration of lanes change?


Yes, there will be designated turn lanes on Bickford Avenue with a reduction down to one (1) travel lane each direction.