10th Street Improvements
Project overview
The 10th Street project will replace old, inadequate public utility infrastructure with repair and resurfacing of the road. The project will take place entirely within the City right-of-way of 10th Street from Avenue D to Maple Avenue. Additional work within Avenue A right-of-way is proposed from 10th Street to 11th Street.
| Timeline | Summer 2025 |
| Project Status | Pre-construction |
| Funding | Transportation Improvement Board (TIB) grant funding is being utilized for this project. |
What to expect
The 10th Street Overlay project is set to grind and overlay the project area following installation of new water, sewer, and stormwater utilities, as well as full depth repair of failing road sections. All existing utility services will be reconnected to the new installed infrastructure. Expect lane closures and traffic revisions on 10th Street and Ave D during construction. Some customers may experience brief interruptions to utility services.
This project entails:
- Replacing the existing water main in 10th Street and in Avenue A. New services to connect to existing meters.
- Replacing the existing sanitary sewer in 10th Street and in Avenue A. New side sewers will connect to existing customer side sewers at the property line.
- Minimal improvements, such as extra catch basins, may be added necessary to improve drainage.
- New ADA ramps at road intersections if existing ramps are out of compliance, or none currently exist.
- Final restoration for 10th Street and Avenue A will involve a complete grind and overlay.
The Contractors information will be posted once awarded the project. Residents and businesses may coordinate directly with the contractor and independent of the City for private construction opportunities subject to permit requirements. Door hangers and flyers will be delivered prior to start of construction with City and Contractor contact information.
| May 2025 | Project advertised for competitive bidding |
| June 2025 | Contractor selected |
| July 2025 | Construction begins |
| December 2025 | Construction scheduled for completion |
| 10th Street (Avenue D - Maple Avenue) Improvement* | $6.48 million |
| Avenue D (2nd Street - 10th Street) Improvement | $4.6 million |
*Awarded Transportation Improvement Board Arterial Preservation Program Grant in 2023. Budget includes City match which is 15% of theproject cost.
1. Will my driveway access be impacted?
Driveway access may be restricted for a short time, but the Contractor will make efforts to allow free ingress and egress with driveways.
2. Will there be any road or intersection closures?
Currently no full road or intersection closures are anticipated, however this may change during construction with adequate notice provided. There will be traffic control for any lane closures or work within vehicle travel lanes and Variable Message Signs (VMS) will be set out to deliver traffic control notices.
3. Will there be any work on my property?
The only portion of work that will require coordination with property owners will be reconnecting the water and sewer services to each property. Three (3) days' notice will be provided prior to any work on active water and sewer services.
Robert Endsley
City of Snohomish Project Engineer
360-282-3174
Email Robert